Shell Pecten

Introduction


The History

Why is our history so important? . . . whilst we can’t see into the future we can influence and predict likely outcomes by learning how things have been done in the past. Expro has a very rich history . . . one of the most impressive things being the way in which the organisation has constantly transformed itself over the years to meet changing business challenges . . . from a drilling organisation in the late 60’s to an engineering organisation through the 70’s and 80’s to a business focused organisation in the 90’s and beyond.

These transformations give us the confidence to adapt to meet whatever challenges the future may bring.

 

 

1962/63

2D seismic survey acquired by Shell/Esso/BP. BP backs out later from a joint venture when it became clear that no pre-emptive rights would be accepted by the UK Government.

 

 

1964

Agreement with Shell and Esso to exploit UK Continental Shelf Gas Reserves (1/1/1964). First London office in Shell Centre with 3 employees (George Williams, MD; June Webster, Secretary; John Tomlinson, Exploration Manager).

 

September

75 licence blocks granted to Shell/Esso in the UK Government's first ever allocation of petroleum production licences.

 

1965

January

Southern operations base set up in Lowestoft, total Expro staff increased to 12. Further offices set up in Hartlepool and Aberdeen (above Church of Scotland bookshop in Union Street).

 

April

Shell Expro's first exploration well spudded 140 miles off Sunderland in 75 feet of water, with "Mr. Cap" rig. At costs of £766,000 the well was dry and the rig was damaged whilst jacking down.

May

First lease of Torry Quay in Aberdeen.

 

 

November

Shell/Esso granted 14 new licences in second round of licensing.

 

1966

April

Leman field discovered in 120 feet of water.

June

Indefatigable field discovered in 99 feet of water.

 

1967

September

Shell Expro's first semi-submersible rig, Staflo, began drilling in Northern waters off Aberdeen.

Northern Operations base set up in Aberdeen. Leman AD and AP installed in June/August and development drilling started straight afterwards.

 

1968

August

First production started from the Leman gas field.

Leman Alpha to Bacton pipeline operational. Start up of Bacton gas plant.

 

1969

May

South East Indefatigable field (SEAN) discovered in 100 feet of water.

September

Announcement of third round of UK licensing.

 

1970

June

Leman BT terminal platform installed.

November

First production from Leman B.

Eleven licences awarded to Shell/Esso.

 

1971

January

Discovery of Auk oil field announced.

August

Fourth round sealed cash bids are submitted. Expro bids £21 million for Cormorant block 211/21.

September

First production from the Indefatigable gas field from Inde J.

December

Jointly owned Shell/Esso and Amoco pipeline from Amoco BT to Bacton operational.

Jointly owned Shell/Esso and Amoco pipeline from Indefatigable IT to Amoco BT operational.

 

1972

February

Leman C on stream.

March

In the final stage of the UK fourth round licensing, Shell/Esso allocated a further 11 blocks in the North Sea.

August

Discovery of the Brent field announced.

September

Discovery of the Cormorant Field (Southern area) announced.

Expro re-organisation: drilling staff moves to Aberdeen. Offices in London, Lowestoft, and Aberdeen now equal in size with 267, 222, and 228 employees.

 

1973

March

Indefatigable K on stream.

April

Tullos Phase 1 opened.

June

Discovery of the Dunlin field announced.

November

Jointly owned Shell/Esso and Amoco pipeline from Leman BT to Bacton operational.

 

1974

May

Single Buoy Mooring system, ELSBM, installed in the Auk field.

Tullos Phase 2 opened. 50 new houses for International staff on order. New Torry site approved.

July

Auk jacket successfully installed.

Discovery of the North Cormorant field announced.

August

Transport agreement with Hutton and Thistle fields signed, this secures the viability of the Brent oil pipeline.

Production from Leman D.

Brent development costs increase from £900 Million (11/74) to £1,300 Million (5/75) with about 50% of the increases related to inflation.

 

1975

January

Petroleum Revenue Tax introduced.

February

Compression platform Leman AK installed.

Compression platform Leman BK installed.

April

Discovery of the Tern field announced.

August

Brent Flare installed.

Brent B platform installed.

December

Auk A production began.

 

1976

The Shell Group issue the Statement of General Business Principles, which is universally adopted by all Shell companies.

February

First oil from the Auk field arrived at Teesport refinery.

May

Brent A jacket installed.

Work started on the FLAGS gas line to St Fergus, Scotland.

Discovery of the Eider field announced.

June

Spar installed in the Brent field.

July

Brent D platform installed.

August

Fifth round of licensing announced.

November

Brent field production began from Brent B (into storage).

December

First tanker loaded crude at Brent Spar.

 

1977

May

Construction on St Fergus Gas Plant started.

June

Dunlin A platform installed.

Brent B suspends production for one year because of Government restrictions to flaring.

July

Discovery of the Fulmar field announced.

Brent Air Traffic Control Centre set up. By Oct 1980 it had logged the first 500,000 flights making it the second busiest in the UK after Heathrow.

November

Brent D production began.

Tullos Phase 3 opened, increasing office space from 240 to 400 (with additional 100 in the Temp block).

 

1978

May

Cormorant A platform installed.

June

Brent A production started.

Brent C platform installed.

FLAGS pipeline complete.

July

Fulmar template installed and production drilling begun.

August

Dunlin begins production (into storage).

October

Indefatigable L onstream.

November

Sullom Voe oil terminal onstream.

Brent System pipeline onstream.

First Dunlin oil flowed into Sullom Voe via the Brent System pipeline.

 

1979

March

Sixth round of licensing allocations.

Western Leg gas line between Cormorant A and Brent A platforms completed.

July

Fulmar wellhead jacket installed.

September

Tullos Phase IV opened by Margaret Thatcher, office space now 850.

October

Construction at Mossmorran and Braefoot Bay

November

Brent oil pumped to Sullom Voe via Cormorant A.

December

Cormorant A production started.

Fabrication of MSV Stadive begun.

 

1980

June

Fulmar A jacket installed.

 

1981

January

Production commenced from Cormorant South.

March

Seventh round licensing Shell/Esso awarded two blocks.

Shell/Esso/BNOC awarded two blocks.

May

SALM (single anchor leg mooring) installed in the Fulmar field.

Royal opening of Sullom Voe Terminal.

June

Brent C production start-up.

July

FSU (floating storage unit) connected to the SALM in the Fulmar field.

December

Western Leg pipeline in operation.

 

1982

January

Leman E jacket installed.

February

Production drilling started on Leman E.

First oil production Fulmar wellhead jacket.

First oil production North Cormorant.

April

First offtake of crude from Fulmar FSU.

Loadout and official launch of Underwater Manifold Centre (UMC).

May

St Fergus Gas Plant onstream.

FLAGS pipeline opened. First gas from Brent delivered to St Fergus.

Installation of Underwater Manifold Centre (UMC) on Central Cormorant.

First oil from main platform Fulmar A.

August

Module 2 commissioned, St Fergus.

October

Royal opening of St Fergus Gas Plant.

December

MSV Stadive delivered after successful trials.

 

 

1983

February

Shell Esso awarded two blocks in the eighth licensing round.

May

First production from the UMC received at Cormorant A.

Shell/Esso awarded seven more blocks in the eigth licensing round.

August

Leman E platform onstream.

September

The final section of the NGL pipeline linking St Fergus to Mossmorran was installed.

December

MSV Stadive completed the first season of operations in the Northern North Sea.

 

1984

Award winning Phase V building opened, increasing office space to 1700.

May

NGL pipeline from St Fergus to Mossmorran completed.

 

One billionth barrel of crude oil was loaded from Sullom Voe oil terminal.

July

The first section of the subsea pipeline from Fulmar to St Fergus was completed.

The first NGLs were received at Mossmorran.

September

The first LPG was exported from Mossmorran.

November Official opening of the Mossmorran Fractionation plant and Braefoot Bay Marine Terminal.

December

Sean South and North wellhead jackets were installed.

 

1985

Target Zero Safety campaign launched.

April

Indefatigable M platform installed.

May

Sean PP jacket installed.

June

Shell/Esso awarded eight blocks in the ninth licensing round.

July

Sour gas module installed on the Fulmar A platform.

October

First production from the Indefatigable M.

December

Leman F and G jackets installed.

Sean PP and PD topsides installed.

 

1986

Low oil price results in significant reduction in programme activities.

March

Shell awarded interests in seven licences in the first UK onshore licensing round.

May

First gas from Fulmar to St Fergus produced.

June

Royal opening of the Mossmorran Fife Ethylene Plant (FEP).

October

Sean Gas Field on stream.

December

Indefatigable N jacket and topsides installed.

 

1987

Shell Expro Activity Review and Challenge (SEARCH) improvement project launched in response to 1986 low oil price.

February

Leman F and G topsides installed.

March

Brent produced its one billionth barrel of oil.

September

Development of the Kittiwake field announced.

First gas from Leman F and G to Bacton.

 

1988

Explosion on Occidental platform Piper Alpha rocked the whole industry and the subsequent inquiry led by Lord Cullen resulted in fundamental changes to the North Sea regulatory framework.

April

Eider jacket installed.

May

Tern jacket installed.

June

Eider and Tern topsides installed.

November

First oil from Eider.

December

World drilling record achieved on Cormorant A.

Fulmar FSU and SALM broke loose.

 

1989

June

First oil from Tern

July

Development of the Gannet cluster announced.

August

Clipper PW jacket and topsides installed

October

Fulmar FSU and SALM reinstated.

1990

6000 directly employed staff.

April

Barque PB and Clipper PT platforms installed in the Sole Pit field.

May

Kittiwake jacket and topsides installed.

July

Kittiwake Loading Bouy installed.

Osprey module installed on Dunlin A.

September

First oil from Kittiwake.

October

First gas from Sole Pit.

 

 

1991

Turnaround Strategy Improvment process launched with a target of improving field life of existing assets by reducing operating costs by 30% by end 1993.

January

First oil from Osprey subsea field into Dunlin platform.

June

Gannet A jacket installed.

July

Development of the Nelson field announced.

 

1992

April

Gannet integrated deck installed.

November

Development of Galleon gas field announced.

First oil from Gannet.

 

 

1993

Long term partnering with contractors commenced with the award of Maintenance and Modifications Services Contractor (MMSC) contracts.

April

£1.3 billion Brent redevelopment project announced.

Nelson jacket installed.

June

Galleon jacket installed.

August

Nelson integrated deck installed.

 

1994

February

Design contract awarded for Floating Production Storage and Offtake (FPSO) facility for the potential development of a number of discoveries in the Central North Sea.

April

The Vinga single turret loading (STL) system replaces the floating storage unit (FSU) at Fulmar.

July

Brent Bravo shuts down for re-development.

August

Development of Pelican field announced.

September

Development af East Sean announced.

October

First gas production from Galleon.

December

Development of Schooner gas field announced.

 

1995

4000 directly employed staff.

 

Cost Review in Expro Study Team (CREST) improvement project identified a £760 million opportunity gap over 5 years and recommended a fundamentally different business model for managing Shell Expro.

February

Development of Teal, Teal South and Guillemot A announced, using FPSO, Anasuria.

Abandonment plans for deep water disposal of Brent Spar announced.

June

Plans for disposal of Brent Spar in deep water halted.

July

Permission granted to moor Brent Spar in Norwegian Fjord while new disposal options are considered.

August

Brent Bravo resumes production after long term shutdown for re-development.

 

1996

Focus on Reputation Management as a key management process.

January

Development of the Heron Egret and Skua fields (Heron Cluster) announced as part of the Eastern Trough Area Project (ETAP) operated by BP.

Pelican production begins into Cormorant A.

April

Brent C begins shutdown for redevelopment.

July

Development of Curlew field announced.

August

List of 30 schemes announced for Brent Spar disposal.

September

Gannet A is one of the first fields to be developed using horizontal well technology and tender assisted drilling.

October

First oil produced from Anasuria FPSO.

Development of Mallard field announced.

Brent C resumes production after re-development.

Development of Kingfisher field announced.

Development of Shearwater field announced.

November

First seminar in the Brent Spar dialogue process held in London.

 

1997

Industry Step Change in Safety programme launched to make a 50% improvement in industry wide safety performance.

 

Brent Re-development project completed.

 

1998

Employee Value Proposition (EVP) work started to ensure that Shell Expro continues to be a Great Place to Work.

 

1999

Shell Expro Environmental Management System independently certified to ISO 14001 International Standard.

 

Brent Spar decommissioned.

 

Shell Mex House sold, New Business Development Team moved to Aberdeen.

 

 

2000

2600 directly employed staff.

 

Shearwater platform commissioned.

 

Blyth Offshore Wind Farm commissioned.

 

2001

Accountability for Safety campaign launched.

 

First gas from Brigantine field.

 


  Use of, and copying from, this site is subject to our terms and conditions. Please read our privacy policy.